4-week forecast window open. 5 disciplines have not submitted their resource forecast: Electrical, Structural, Telecom, Automation / BMS, Fire Protection.

Workforce Capacity

Capacity overview per project and business development: required vs actual people per week, current headcount and HR objective by discipline.

Disciplines

5

Peak required

404

people in a single week

Peak headcount

395

total people available

HR objective

510

target by W53

Required vs actual vs headcount

TeamDisciplineMetricW32W33W34W35W36W37W38W39W40W41W42W43W44W45W46W47W48W49W50W51W52W53Total ResourceResource BalanceTotal HoursHours Balance
Shelley Barradas / Ivo LapaArchitectureRequired29.534.537.554.562.567.7569.7554.2553.2546.7554.7567.7567.7562.7560.7567.568.568.565.560.560.501914.5110472,96641,310
Actual29.2531.2534.2542.2547.255658.2550.7549.7527.523.519.515.51.51.51.51.51.50.50.50.50810.531,656
Total Headcount3436373840434545454850525455555555555555550
HR Objective3535353540404040454545455050505050555555600
Tor Helge / DanielStructural & CivilRequired192424.523.527.525.7527.752424.522.52329.530.2530.7530.7534.535.535.53431.531.501030.0542539,05515,755
Actual14.7517.7517.2516.2525.7524.526.25222321.2519.7522.2523.511.511.59.55.55.51.51.51.50604.7523,300
Total Headcount3333333434343535373737373737373737373737370
HR Objective3333333335353535404040404042424242424242450
Carlos L / Eric OMechanicalRequired36.538.539.537.539.536.254143.539.542.551.571.2574.7569.2567.2574767673.5606001875.5118071,33444,152
Actual35.7536.7536.7535.7538.25333838.533.530.2525.251514.51.51.51.50.50.50.50.50.5069527,182
Total Headcount3537404545464648495555606570707375757575750
HR Objective4042454750525557596065657072747578808590950
Jorge PaivaElectricalRequired404243575958.2586.559.559.5595879.7584.2579.2577.2585868682.5666602288.5143987,13453,606
Actual38.7539.7539.7554.7557.255373.5413930.7527.7526.5260.50.50.50.50.50.50.50.50849.7533,528
Total Headcount5862626263656767677073758085909597989898980
HR Objective606365677073757780838587901001051101121151201231250
Joao T / Joao C / Levi P/ Artur MExecution Design + Prefab DesignRequired909188.585.592.57883.5848485.7589.7595.7597.75101.25104.25127135138143161165036322369137,70688,136
Actual57.2559.255659.55859.255863.7563.756563.56770.5181212121212121201262.7549,570
Total Headcount951001051071101121171201221251231251281301301301301301301301300
HR Objective971001051071101151201251271301351401451501551601651701751801850
Programme totalTotal Required215230233258281266308.5265.25260.75256.5277344354.75343.25340.25388401404398.53793830
Total Actual175.75184.75184208.5226.5225.75254216209174.75159.75150.2515033272520201515150
Total Headcount2552682772862923003103153203353383493643773823903943953953953950
HR Objective2652732832893053153253343513583703773954144264374474624774905100