4-week forecast window open. 5 disciplines have not submitted their resource forecast: Electrical, Structural, Telecom, Automation / BMS, Fire Protection.

Project Forecasting

Weekly required vs actual design people for each project, broken down by discipline.

ProjectWS5

Seinajoki Phase 1 (3 Buildings)

Window W32–W53 · snapshot W38 260914

Design manager
Filipe Fernandes
Discipline leads
André Raimundo / Iikka Ylihärsilä / Tiina Salmen / Gonçalo Gonçalves / Teresa Costa
Status
Active - P1
Country
Finland
IT load
110 MW

Required

658

person-weeks in window

Actual

424

allocated in window

Gap

234

required minus actual

Peak week

41

people required

Required vs actual

Seinajoki Phase 1 (3 Buildings) · people per week

Forecast

Seinajoki Phase 1 (3 Buildings) · planned and actual per discipline, week by week

9-week window · W39–W47
DisciplineSeriesW39W40W41W42W43W44W45W46W47
ArchitecturePlanned1212121212101087
Actual121212121210···
Structural & CivilPlanned333333333
Actual333333···
MechanicalPlanned666666333
Actual666666···
ElectricalPlanned666666333
Actual666666···
Execution Design + Prefab DesignPlanned121212121414121212
Actual141212.512.514.514···