ProjectHyperscale Client A
4-week forecast window open. 5 disciplines have not submitted their resource forecast: Electrical, Structural, Telecom, Automation / BMS, Fire Protection.
Change Management & Deviations
Internal deviations are approved by the Design Manager with a technical justification. External deviations trigger a commercial variation.
CHG-001Internal deviation2026-08-19
Switch from 2N to N+1 UPS topology in Data Hall B
Client load profile revised down by 18%. Redundancy target still met per Tier III requirements.
ElectricalImpact: CostRaised by Colm Byrne
CHG-002External commercial deviation2026-08-24
Client requested additional generator for future phase
Client instruction CI-042. Requires variation order and schedule re-baseline.
Mechanical / HVACImpact: Schedule + CostRaised by Aoife Kelly