4-week forecast window open. 5 disciplines have not submitted their resource forecast: Electrical, Structural, Telecom, Automation / BMS, Fire Protection.

Change Management & Deviations

Internal deviations are approved by the Design Manager with a technical justification. External deviations trigger a commercial variation.

CHG-001Internal deviation2026-08-19

Switch from 2N to N+1 UPS topology in Data Hall B

Client load profile revised down by 18%. Redundancy target still met per Tier III requirements.

ElectricalImpact: CostRaised by Colm Byrne
CHG-002External commercial deviation2026-08-24

Client requested additional generator for future phase

Client instruction CI-042. Requires variation order and schedule re-baseline.

Mechanical / HVACImpact: Schedule + CostRaised by Aoife Kelly