4-week forecast window open. 5 disciplines have not submitted their resource forecast: Electrical, Structural, Telecom, Automation / BMS, Fire Protection.

Client Permitting & Submittals

Deliverables released from the Delivery Charter into the Master Document Register, tracked through to client approval.

Every MDR line originates from an approved charter activity.

6 of 6 documents
Document codeDisciplineTitleRevForecast dateSubmittedClient statusAction
MDR-ELE-001ELEBasis of Design – ElectricalR22026-09-042026-09-03ApprovedClosed out
MDR-MEC-001MECCooling Concept ReportR12026-09-052026-09-05Approved with commentsClosed out
MDR-CIV-001CIVCivil Concept PackageR12026-09-062026-09-08Pending
MDR-TEL-001TELCabling Backbone ConceptR02026-09-11Pending
MDR-FIR-001FIRFire Strategy ReportR12026-09-122026-09-14RejectedClosed out
MDR-STR-001STRStructural Calculations – Data HallR02026-09-26Pending