ProjectHyperscale Client A
4-week forecast window open. 5 disciplines have not submitted their resource forecast: Electrical, Structural, Telecom, Automation / BMS, Fire Protection.
OpenSpace & Issue Tracker
Site queries captured against 360° imagery and routed to the responsible discipline.
Each RFI is linked to the capture position where it was raised.
RFI-014OpenHigh priority · 3 days open
Clash between busway route and chilled water header at grid D4
OpenSpace 360° · Level 1 / Data Hall AElectricalRaised by Site – Nordics DC1
RFI-015AnsweredMedium priority · 8 days open
Confirm slab penetration size for MMR containment
OpenSpace 360° · Level 0 / MMRTelecomRaised by Site – Nordics DC1
RFI-016OpenHigh priority · 1 days open
Generator yard bund height differs from civil drawing
OpenSpace 360° · External / Gen YardCivilRaised by Project Exec
RFI-017ClosedLow priority · 21 days open
Sprinkler head spacing under raised floor void
OpenSpace 360° · Level 1 / Data Hall BFire ProtectionRaised by Client Rep