ProjectHyperscale Client A
4-week forecast window open. 5 disciplines have not submitted their resource forecast: Electrical, Structural, Telecom, Automation / BMS, Fire Protection.
Design Schedule & Interdependencies
Simplified Gantt showing how each discipline's design work links to the preceding package.
W1W2W3W4W5W6W7W8W9W10W11W12
Site & civil concept
Civil
100%
Structural frame design
Structural · after S1
65%
Electrical schematics
Electrical · after S2
45%
Cooling plant detailed design
Mechanical / HVAC · after S2
30%
Telecom pathways
Telecom · after S3
15%
BMS integration design
Automation / BMS · after S4
10%
Fire suppression detailed design
Fire Protection · after S4
0%
ElectricalMechanical / HVACCivilStructuralTelecomAutomation / BMSFire Protection